…events Deployments today are only visible as a side effect of a service state change (service.deployed/service.upgraded), with no way to observe the orchestration act itself: when a rollout started, when it finished, or how long it took. This adds deployment as its own subject with the standard queued/started/finished lifecycle, giving DORA-style tooling an explicit deployment-duration/outcome fact independent of the resulting service entity. service.deployed/service.upgraded are unchanged; whether to deprecate them is a separate decision left for a follow-up once deployment.* has implementation experience. The original proposal also included a targetRollout subject to model fan-out to multiple destinations within one deployment; that's split into a separate follow-up PR pending more implementation experience. Signed-off-by: xibz <bjp@apple.com>
…ished events Follow-up to the deployment subject: targetRollout models a single destination within a deployment's environment (a region, canary slot, or named blue/green slot), giving environment a first-class inbound link to what was rolled out into it, and giving consumers per- destination outcome/failureType detail when a deployment fans out to more than one target. This mirrors the pipelineRun/taskRun split already in the spec: a parent orchestration entity (deployment/pipelineRun) fans out to child execution units (targetRollout/taskRun), each with the standard queued/started/finished lifecycle. Stacked on the deployment subject (see the deployment branch/PR) since targetRollout's deploymentId reference and docs build on it. Signed-off-by: xibz <bjp@apple.com>
| { | ||
| "$id": "cdevents/_defs/targetrollout", | ||
| "term": "TargetRollout", | ||
| "definition": "A TargetRollout is a specific destination within an environment to which a release unit may be deployed and made available. A TargetRollout is always contained within an environment. Multiple TargetRollouts may exist within a single environment.", |
There was a problem hiding this comment.
I'm confused here. I thought a TargetRollout was an activity that can be queued, started and finished . In here it is defined as a destination, which seems inconsistent. Can you clarify?
There was a problem hiding this comment.
Good catch! The definition was wrong, not the model. A targetRollout is the activity: rolling a deployment out to one target within an environment. The destination itself is already captured by target and environment. I've reworded the definition, examples, and counterExamples accordingly (and moved "a canary slot" to counterExamples, since that's the place, not the rollout). I'd rather not rename to targetRolloutRun: unlike pipeline, there's no static "rollout" definition entity for the Run to distinguish from, "rollout", like "deployment", already names the act.
| "required": [ | ||
| "name", | ||
| "target", | ||
| "environment", | ||
| "artifactId" | ||
| ] |
There was a problem hiding this comment.
I was expecting the deploymentId to be required. Could you describe a use case where it would not be set?
There was a problem hiding this comment.
Agreed, I couldn't come up with a solid case for a rollout without a parent deployment. A producer with a single destination and no aggregate can just emit deployment events. deploymentId is now required on queued, started and finished.
| "required": [ | ||
| "name", | ||
| "target", | ||
| "environment", | ||
| "artifactId", | ||
| "outcome" |
There was a problem hiding this comment.
NIT: this could be:
"required": ["name", "target", "environment", "artifactId", "outcome"],
"if": { "properties": { "outcome": { "const": "failure" } } },
"then": { "required": ["failureType"] },
"else": { "not": { "required": ["failureType"] } }to enforce that failureType must be there in case of failure and must not be there in case of success.
That said, we don't have that in other schemas, although it would be nice to add.
There was a problem hiding this comment.
I like it, but since no other schema uses conditional validation yet, I'd rather not make this one the odd one out. I'll open a follow-up that applies it across all outcome-bearing schemas together. That follow-up also needs to settle whether failureType should be allowed with outcome: error (your else branch would reject it).
| "id": "test123" | ||
| }, | ||
| "artifactId": "pkg:oci/myapp@sha256%3A0b31b1c02ff458ad9b7b81cbdf8f028bd54699fa151f221d1e8de6817db93427", | ||
| "deploymentId": "mySubject123" |
There was a problem hiding this comment.
Shouldn't this be different from the subject.id? I think having the same value is confusing.
There was a problem hiding this comment.
Agreed, that made the example read as if the rollout were the deployment. The parent now has its own id (myDeployment123) in all three targetrollout_* conformance examples.
- Redefine targetRollout as the act of deploying a release unit to a single destination, not the destination itself. The destination is already identified by the target and environment fields, and the queued/started/finished lifecycle only makes sense for an activity. Examples and counterExamples updated to match. - Make deploymentId required on queued/started/finished: a target rollout is always part of a deployment. - Give the parent deployment a distinct id in the targetRollout conformance examples so it no longer reads as the subject itself. Signed-off-by: xibz <bjp@apple.com>
|
@afrittoli - thanks Andreaa! Can you take a look again? |
afrittoli
left a comment
There was a problem hiding this comment.
Thanks for the updates, I still have some questions, I'm sorry I missed this in the initial review.
| |-------|------|-------------|----------| | ||
| | id | `String` | See [id](spec.md#id-subject)| `rt-us-east-1-8f3a2c` | | ||
| | source | `URI-Reference` | See [source](spec.md#source-subject) | `/cd/deploy-controller` | | ||
| | name | `String` | Name of the target rollout | `canary`, `us-east-1`, `blue-slot` | |
There was a problem hiding this comment.
The name here still seems to refer to the targetRollout as being a place rather than an activity
There was a problem hiding this comment.
Agreed, name was a leftover. The rollout is identified by subject.id, the same way deployment is, and the destination by target. I've removed name from the subject, all three predicates and the conformance examples.
| { | ||
| "$id": "cdevents/_defs/targetrollout", | ||
| "term": "TargetRollout", | ||
| "definition": "A TargetRollout is the act of deploying a release unit to a single destination within an environment, as one part of a Deployment. The destination itself is identified by the TargetRollout's target and environment.", |
There was a problem hiding this comment.
I would say the deployment is performed against a destination environment, or a destination in an environment.
There was a problem hiding this comment.
That reads better, thanks. I've adopted it, with one change explained in the next thread: it now reads "the act of deploying a release unit against a destination in a tier, as one part of a Deployment."
| | target | `URI-Reference` | Location identifier of where the artifact is being deployed to | `cdevents:v0:argo::my-org:prod-cluster:environment:us-east-1` | | ||
| | environment | `Object` ([`environment`](#environment)) | Reference to the containing environment | `{"id": "production"}` | |
There was a problem hiding this comment.
The relationship between target and environment is a bit unclear to me.
The latter is a reference to an environment, the subject in CDEvents, which is clear.
The target I guess represents a specific location within that environment, is that correct?
Is there any connection between the data in the URI-reference and that in the environment?
There was a problem hiding this comment.
You've put your finger on the real problem. The field was meant to be the logical environment (production), because it's what consumers key on to compute lead time to deploy. But the environment subject is defined as "a platform which may run a service", and in practice it's widely used to mean a specific cluster. So "target is a location within the environment" reasonably reads as "a cluster within a cluster".
Rather than redefine environment, I've given the logical concept its own name: tier (a string, e.g. production, staging), defined in schemas/_defs/tier.json. target is the concrete destination within that tier, e.g. the us-east-1 cluster that's part of production. One tier contains many targets, and a deployment to production fans out into one targetRollout per target. target is opaque to CDEvents, but it must identify a destination belonging to the tier.
The same rename applies to deployment in #319, and the environment subject section now points to tier for anyone looking for the logical environment. The example is consistent too: "tier": "production" with target: cdevents:v0:argo::my-org:production:cluster:prod-us-east-1.
- Remove name: the rollout is identified by subject.id, like deployment, and the destination by target. - Replace the environment reference with tier (the logical environment, used to compute lead time to deploy); target is the concrete destination within it, typically a cluster. - Reword the definition: the act of deploying an artifact against a destination in a tier. - Version the new targetRollout events 0.1.0-draft and replace "release unit" with "artifact", matching the deployment review. Signed-off-by: xibz <bjp@apple.com>
Follow-up to #319 (
deployment.queued/started/finished), per @afrittoli's review: landingdeploymenton its own first, withtargetRolloutproposed separately here now that there's a concrete use case and one open PR of implementation experience to point to.What this adds
targetRollout— the act of deploying a release unit against a single destination within a tier (for example the us-east-1 cluster withinproduction, or a named blue/green slot), as one part of adeployment. It has the standardqueued/started/finishedlifecycle, a requireddeploymentIdback-reference to its parentdeployment, andfailureTypeonfinishedfor per-destination failure detail.Each
targetRolloutcarries:tier— the logical environment (production,staging, …) the rollout belongs to: the value consumers key on to compute lead time to deploy. Defined inschemas/_defs/tier.json(introduced in feat(deployment): add deployment subject and queued/started/finished events #319).target— the concrete destination within that tier, typically a cluster.Why
tierand notenvironmentThe
environmentsubject is defined as "a platform which may run a service", and in practice it is widely used to mean a specific cluster. Using it for the logical environment made "targetis a location within theenvironment" read as "a cluster within a cluster". Rather than redefine an existing subject, the logical concept gets its own name, and theenvironmentsubject section points totierfor anyone looking for it.Why this isn't a new execution model
The concern raised on #319 was that giving
targetRolloutits own independent lifecycle "encodes one execution model." But this is the same shape the spec already has forpipelineRun/taskRun: a parent orchestration entity fans out to child execution units, each with its ownqueued/started/finished.targetRolloutunderdeploymentis that same pattern, not a new one. A producer that genuinely fans a deployment out to multiple destinations already has to track per-destination timing to coordinate the rollout in the first place — this just gives that internal fact a standard external shape. A producer that deploys to exactly one destination, or that calls a single atomic multi-region API with no per-destination visibility, simply doesn't emittargetRollout— same as any other optional CDEvents subject.Together,
tierandtargetalso make "what was rolled out to production, and where" a direct query overtargetRolloutevents. Today it has to be inferred fromserviceevents, whoseenvironmentreference points the other way: from the running entity back to whatever platform it happens to run on.Depends on #319 — this diff will be just the
targetRolloutadditions once that merges.Submitter Checklist
As the author of this PR, please check off the items in this checklist: